Cleanspark reported a $987.1 million fiscal 2026 net loss on Tuesday as the company outlined a strategy to potentially sell more bitcoin than it mines each quarter, using its digital asset reserves to finance expansion into artificial intelligence infrastructure.
During the November 24 earnings call, President and Chief Financial Officer Gary Vecchiarelli explained that Cleanspark has not established a minimum bitcoin treasury balance and intends to manage its holdings according to market conditions and capital requirements. In the September quarter, the company sold 2,102 BTC while producing 1,708 BTC, exceeding production by 23 percent.
"We see the selling of a small amount of bitcoin in excess of the quarterly production to be one way of derisking," Vecchiarelli said. "We're going to use that capital to make sure that we prevent dilution or bringing on additional debt just to grow the company."
Financial Performance and Market Headwinds
Cleanspark swung from a $364.5 million profit in fiscal 2025 to a $987.1 million loss in fiscal 2026. Annual revenue contracted 25 percent to $576.5 million, while fourth-quarter revenue fell 46 percent year over year to $120.9 million.
Roughly two-thirds of the annual loss resulted from noncash adjustments to bitcoin valuations. Bitcoin closed the fiscal year near $83,600, compared with approximately $114,000 a year earlier. The company also recorded $177.1 million in impairment expenses related to converting its Sandersville, Georgia mining facility into an AI data center.
Mining production declined 8 percent to 7,253 BTC during fiscal 2026, while average hashrate decreased 21 percent to 36 exahash per second. At September 30, Cleanspark held 13,530 BTC in its treasury, valued at $1.13 billion, alongside $204.8 million in cash and cash equivalents.
Transformation to AI Infrastructure Provider
Cleanspark's changing treasury strategy accompanies a capital-intensive shift away from bitcoin mining. In July, the company secured a 20-year, $6.6 billion triple-net lease for its Sandersville campus and financed development through $2.276 billion in senior secured notes carrying a 7.875 percent interest rate and maturing in 2031.
Founder and CEO Matt Schultz told analysts that the company's focus is to "convert scarce grid-connected power into long-term contracted cash flow." The first Sandersville data hall is scheduled for delivery in November 2027, with completion anticipated in spring 2028.
Cleanspark also is advancing two Texas developments representing up to 885 megawatts of secured and planned electrical capacity, though regulatory uncertainty has complicated lease negotiations. Management indicated that substantial investments in new bitcoin mining equipment are no longer a priority.
Industry-Wide Bitcoin Sales Accelerate
Cleanspark is not alone in drawing down bitcoin reserves. Since September 30, publicly traded mining companies including Mara, Hut 8, and Riot Platforms have collectively disclosed substantial bitcoin sales. Mara and Hut 8 together sold over 15,745 BTC worth approximately $1.28 billion, with Mara directing $750 million toward repaying bitcoin-backed loans and Hut 8 deploying proceeds toward share repurchases. Riot Platforms sold 20,264 BTC through September, raising approximately $1.5 billion primarily for data center development.
The selling reflects a broader departure from the industry's accumulation strategy. According to Glassnode analysis from November 18, publicly traded bitcoin miners have divested nearly half their holdings since January 2026 as capital demands mount and AI infrastructure competes for investment.