Norway's transmission system operator Statnett paused new grid reservations for data centers on November 9, citing overwhelming demand for electricity. The freeze is expected to remain in effect until at least August 1, 2027, when a new connection system takes effect. On the same day, the Norwegian government unveiled a licensing scheme designed to exclude new cryptocurrency mining operations from the country.
Requests for data center connections total roughly 32-34 GW, exceeding Norway's entire national peak demand of just over 25 GW. Currently, only 800 MW of data center capacity is connected, with 4.2 GW reserved, 9.1 GW queued for approval, and approximately 18 GW in requests for new connections. Statnett cited concerns about both volume and grid reliability, noting that large computing facilities can cause volatile power-draw changes that destabilize the grid.
Under the proposed licensing regime, new cryptocurrency mining sites are explicitly barred. The government stated that crypto mining does not serve the public interest, while AI computing and other projects deemed to deliver societal benefits will receive priority. Norway currently hosts six crypto mining data centers consuming about 0.2 GW of energy.
Existing data center operations will not be shut down, though they face restrictions on expansion. Current crypto miners are subject to growth limits. The full licensing framework is expected to be detailed in autumn 2027.
The policy represents a shift from Norway's traditional first-come, first-served approach to allocating its abundant hydropower. The country is moving toward a system that ranks electricity users by perceived societal value, explicitly prioritizing AI development over cryptocurrency mining when deciding grid access for scarce capacity.